X.1 Delivery Notice. Upon completion of each Deliverable described in Exhibit A (Statement of Work), Developer shall provide written notice to Client ("Delivery Notice").
X.2 Acceptance Period. Client shall have ten (10) business days from receipt of the Delivery Notice to conduct testing and submit a written Rejection Notice ("Acceptance Period"). The Rejection Notice must identify each claimed defect with specificity, including the steps to reproduce it, the expected behavior, and the actual behavior observed.
X.3 Defect Severity Tiers. Defects identified during the Acceptance Period shall be classified as follows:
| Severity | Label | Definition | Blocks Acceptance? |
|---|
| S1 | Critical | Core deliverable is non-functional; no workaround exists | Yes |
| S2 | Major | Primary feature significantly impaired; workaround exists | Yes |
| S3 | Minor | Feature functions but with degraded behavior | No |
| S4 | Cosmetic | Visual or presentational issue; no functional impact | No |
X.4 Blocking Defects Only. Client may reject a Deliverable only on the basis of S1 or S2 defects. S3 and S4 defects shall be logged to a punch list and addressed by Developer within 30 calendar days following acceptance. S3 and S4 defects do not entitle Client to withhold payment.
X.5 Deemed Acceptance on Silence. If Client does not deliver a written Rejection Notice within the Acceptance Period, the Deliverable shall be deemed accepted as of the last day of the Acceptance Period.
X.6 Deemed Acceptance on Use. If Client deploys the Deliverable to a production environment or permits end users to access it at any time, the Deliverable shall be deemed accepted as of the date of such deployment or access, regardless of whether the Acceptance Period has elapsed.
X.7 Cure Period. If Client submits a timely Rejection Notice citing S1 or S2 defects, Developer shall have 15 business days to remediate and re-deliver. The Acceptance Period restarts upon re-delivery. If the re-delivered Deliverable is accepted or deemed accepted, payment becomes due within five (5) business days.
X.8 Change Orders. Any request that is not expressly described in Exhibit A constitutes an out-of-scope request and requires a written Change Order signed by both parties before work begins. Developer's agreement to discuss or estimate a requested change does not constitute a commitment to perform it under the original Agreement price.